Lightning protection

Does my building need a lightning protection system?

In India it is required by Regulation 38 of the CEA Regulations 2023 for multi-storeyed buildings above 15 m and for hospitals, hotels, airports, academic buildings, industrial installations and places holding explosive or flammable material. For any other structure, a risk assessment to IEC 62305-2 decides.

Assess your structure

How is the class of lightning protection chosen?

By the risk assessment, not by preference. The assessment compares the risk for your structure with a tolerable risk and returns the minimum class, I to IV, that brings it within limits.

Lightning Risk Assessment

How many down conductors does a building need?

At least two on any attached system, spread around the perimeter at 10 m spacing for Class I and II, 15 m for Class III and 20 m for Class IV, with one at each exposed corner where possible.

Down conductor calculator

Can the building’s steel frame or reinforcement be used as a down conductor?

Yes, if it is electrically continuous. IEC 62305-3 accepts welded, clamped or overlapped and bound reinforcement, verified by a continuity test of 0.2 Ω or less from roof to earth.

Structural earthing

What is the difference between an isolated and an attached system?

An attached system is fixed to the structure and shares lightning current with it. An isolated system keeps the current away from the structure by clearance. Isolated systems suit explosive areas, sensitive contents and roofs crowded with equipment.

Isolated lightning protection

How do I protect equipment on the roof?

Any metal fixture more than 0.3 m high, over 1 m² in area, over 2 m long or within 1 m of the roof edge needs to sit inside the protected volume of an air terminal, or be bonded.

Flat roof lightning protection

Earthing and bonding

What earth resistance value do I need?

For low-voltage safety, IS 3043:2026 sets no minimum electrode resistance: protection is proven by loop impedance and disconnection time. For a lightning protection earth, IEC 62305-3 recommends below 10 Ω. For a substation, the design is governed by touch and step voltage, not a single resistance figure.

Global earthing system

Do I need separate earth pits for the transformer neutral, body, UPS and instruments?

No. IS 3043:2026 lists separate and “dedicated” electrodes among practices that shall not be followed. All electrodes are interconnected into one earthing and bonding network.

Equipotential bonding

What does “double earthing” mean?

Two separate and distinct connections from the equipment to the earthing system. It does not mean two pits. The CEA Regulations require it for equipment above 250 V and for every generator and transformer neutral.

Earthing conductors

Copper, copper-bonded steel or galvanised steel: which electrode material?

It depends on the soil. In soil below 50 Ω·m, and in coastal or saline ground, IS 3043:2026 requires copper, stainless steel or copper-bonded steel. Aluminium is never buried.

Earth electrodes

Is a PE conductor needed if the equipment is already earthed to the grid?

Yes. The protective conductor runs with the supply cable and is what clears the fault. An earth grid is in addition to the PE conductor and never replaces it.

Earthing strips, tapes and cables

When should an earth enhancing compound be used?

Only in high-resistivity ground. IS 3043:2026 limits it to resistivity above 3000 Ω·m, for lightning protection systems, and bars it below 200 Ω·m.

Earth enhancing compounds

What is the best joint for a buried earthing conductor?

An exothermic weld. It is a permanent molecular joint that carries fault current without loosening and has the same corrosion behaviour as the conductor.

Exothermic welding

Surge protection

Type 1, Type 2 or Type 3: which SPD do I need?

Type 1 at the service entrance where there is a lightning protection system or an overhead supply. Type 2 at distribution boards. Type 3 at sensitive equipment. They work as one coordinated system.

SPD Selector

We have a lightning protection system. Do we still need SPDs?

Yes. An external system protects the structure. Without coordinated SPDs to IEC 62305-4, the electrical and electronic systems inside remain exposed, and the bonding SPDs at the entrance are a requirement of the external system itself.

Surge protection by zone

How long can the connecting leads of an SPD be?

Not more than 0.5 m in total. Each metre of lead adds about 1 kV to the voltage the equipment sees.

SPD assemblies

Do data and signal lines need protection too?

Yes. Where power SPDs are fitted, IEC 62305-4 requires SPDs on every other metallic service to the same equipment. An unprotected data line is the usual path of damage.

Data, signal and RF SPDs

Are SPDs mandatory for solar PV?

Yes. Regulation 121 of the CEA Regulations 2023 requires lightning and overvoltage protection for the plant and an SPD in every combiner box.

Rooftop solar protection

Testing and compliance

How often must a lightning protection system be inspected?

Visually every year and completely, with electrical tests, every three years for normal structures. Every year for structures with a risk of explosion or with sensitive systems. Also after any alteration or known strike.

Periodic inspection and testing

How often must earth resistance be tested?

At least once a year, on a dry day in the dry season, for a supplier’s earthing system and for every earthing system above 650 V, with records kept for the Electrical Inspector.

Annual maintenance contract

What will an Electrical Inspector ask to see?

Two earth connections, electrode resistance records, proof that protective bonding has been tested, and loop impedance tested at the origin, for each circuit and for every source.

Monitoring and record

Can LPES certify that my installation complies?

LPES designs, supplies, installs and tests, and reports each item as complies, does not comply or not demonstrated. Statutory acceptance rests with the Electrical Inspector or the authority having jurisdiction.

Certifications & Approvals

Working with LPES

Do you supply products only, or design and install as well?

Both. LPES manufactures lightning, earthing and surge protection components and delivers assessment, design, supply, installation, verification and maintenance under one responsibility.

Lightning to Load

Can you help with a tender BOQ?

Yes. Send the BOQ and drawings. We return item codes, datasheets, specification text and a priced response.

BOQ / Tender Support

Which countries do you serve?

LPES works from India and Europe and supplies projects in India, the Middle East and Europe.

Contact LPES

How do I get datasheets and drawings?

Request them by product family. We send them by email or WhatsApp, usually within one working day.

Downloads & Datasheets
No question matches. Send us yours and we will answer it.
Your question is not here?

Ask an engineer directly.

Describe the site or send the drawing. You get a referenced answer, usually within one working day.

Items have been added to cart.
One or more items could not be added to cart due to certain restrictions.
Added to cart
Quantity updated
- An error occurred. Please try again later.
Deleted from cart
- An error occurred. Please try again later.