Lightning, earthing and surge protection for IT, BPO and storage service facilities
IT parks, BPO centres and storage service providers sell uptime. Their buildings carry rooftop HVAC and telecom masts, their floors run thousands of workstations, and their server and storage rooms hold customer data on UPS and DG power. LPES protects the building and roof, builds one bonded earthing system with a mesh bonding network in the equipment rooms, and protects UPS, network and storage against surges.

Storage Service Provider
Rooftop telecom mast
- Threat
- Telecom and microwave antennas on the highest point of the building.
- LPES measure
- Mast inside the protected zone or fitted with its own air terminal, mast bonded to the LPS, and coaxial screens bonded at the mast and at the building entry.
- Families
Lightning, earthing and surge risks on IT or storage facility sites
Rooftop masts and HVAC
Telecom masts, microwave links, chillers and AHUs on the roof are the first things lightning reaches, and their cables lead straight into the building.
Data and network links
Fibre is immune, but copper links, carrier entries, CCTV and access control lines between buildings carry surges into the core network.
UPS and DG switching
Every grid failure transfers the load to UPS and DG. Switching surges and earth reference changes during transfer stress servers and storage arrays.
Noise and data errors
Poor bonding between racks, raised floors and cable trays causes circulating currents, interference and data errors that are hard to trace.
One coordinated lightning protection, earthing and surge protection system
Four pillars. Connected protection. Clear accountability.
Lightning protection, earthing and surge protection only work when they are designed together. LPES is the four parts of that system in one name.

Lightning protection
The building, roof plant and masts are assessed on lightning risk and on the value of what they house. The structure serves as natural down conductors where continuity is proven, and roof plant and masts sit inside the protected zone.

Power protection
Protection only works if the power system lets it. LPES studies the fault levels, neutral earthing, earth-fault loop impedance and protection settings, so that every PE conductor is sized for its fault current and every protective device disconnects in time.

Earthing protection
One earthing system for the site, with a mesh bonding network in every server, storage and network room, connected to the main earthing terminal and the foundation earth. UPS, DG and transformer neutrals follow one earthing scheme.

Surge protection
Protection follows the power and data paths into the equipment rooms. Type 1+2 at the main board, Type 2 at floor and UPS input boards, Type 3 at critical PDUs and data and coaxial SPDs on every copper line that enters the building.
Products are available in four series, LPES BASIC, LPES SMART, LPES PRO and LPES CENTURY, so the specification can match the duty and the budget of each area of the site.
Earthing and PE conductors: what protects people, and what CEA 2023 requires
An electrode in the ground protects nobody on its own. People and equipment are protected by the conductors that join every frame, panel and pipe back to the main earthing terminal. The CEA Safety Regulations 2023 make these connections mandatory. Select a conductor to see the rule, the sizing and the LPES material. The LPES shields mark where lightning, power, earthing and surge protection apply on the plant, down to the SPD type at each level.
On your IT or storage facility site
UPS, chiller, AHU and pump frames above 250 V get two separate earth connections. Racks, trays and raised floors are bonded with short, low-impedance conductors to the mesh bonding network, and UPS output neutrals follow the earthing scheme.
- Reg 43(v)Every building has protective equipotential bonding that interconnects exposed and extraneous conductive parts.
- Reg 43(ix)Bonding conductors carry the prospective earth-fault current and are tested for effective bonding before energisation.
- Reg 43(xi), (xii)Earth-fault loop impedance is tested so the protective device disconnects in time.
- Reg 43(xiii)The neutral point of every generator and transformer is earthed by not less than two separate connections.
Two points from IS 3043:2026 that change how earthing is specified. At low voltage there is no minimum earth electrode resistance: protection depends on the earth-fault loop impedance and on the protective device tripping in time. And separate “dedicated” or “clean” earth pits for neutral, body, instruments or electronics are not to be used: every electrode joins one interconnected earthing network.
Clause references are to the Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023. Sizing lines follow IS 3043:2026 and IS 732:2019. Confirm against the current official text and state notifications before using them in a tender or inspection.
LPS class, SPD rating and conductor sizes for IT or storage facility projects
The figures engineers look up most, with the clause behind each. Rows marked in red are specific to IT or storage facility sites.
| Item | Value | Source |
|---|---|---|
| Equipment rooms | Common bonding network with a mesh bonding network under equipment rows | ITU-T K.27 · IEC 62305-4:2024 |
| Separate “instrument” earth pits | Not permitted. One interconnected earthing network | IS 3043:2026, 6.3 |
| Links between buildings | Metal-free fibre, or bonded metal ducts with SPDs at both ends | IEC 62305-4:2024, Annex B |
| Drives with high PE current (over 10 mA) | PE of at least 10 mm² copper, or a second PE | IS 3043:2026, 7.6 |
| Rolling sphere radius | 20 / 30 / 45 / 60 m for LPS Class I / II / III / IV | IEC 62305-3:2024, Table 2 |
| Air-termination mesh | 5 / 10 / 15 / 20 m for Class I / II / III / IV | IEC 62305-3:2024, Table 2 |
| Down-conductor spacing | 10 / 10 / 15 / 20 m for Class I / II / III / IV | IEC 62305-3:2024, Table 5 |
| LPS conductor, minimum | 50 mm² in copper, aluminium, galvanised or stainless steel | IEC 62305-3:2024, Table 7 |
| Lightning earth | Ring electrode at least 0.5 m deep, about 1 m from the walls. Aim below 10 Ω | IEC 62305-3:2024, 5.4 |
| Entrance SPD where an LPS exists | Type 1 (Class I). Iimp 25 / 18.75 / 12.5 kA per pole for LPL I / II / III–IV | IEC 62305-4:2024, Table C.3 |
| SPD connecting leads | 0.5 m total or less, line to SPD to earth bar | IEC 62305-4:2024, Annex C |
| Second SPD | Needed when equipment is more than 10 m from the entrance SPD | IEC 62305-4:2024, Annex C |
| Bonding bar to earth | 16 mm² copper, 25 mm² aluminium or 50 mm² steel | IEC 62305-3:2024, Table 9 |
| Disconnection time, TN final circuits | 0.4 s at 230 V, 0.2 s above 230 V | IS 3043:2026, Table 1 |
| Loop impedance, measured | Zs ≤ ⅔ × U0 / Ia | IS 3043:2026 and IS 732 |
| PE and bonding continuity | Within the conductor’s own resistance, tested at about 10 A | IS 3043:2026, Annex E |
The LPS class and the SPD protection level are set by an IEC 62305-2 risk assessment for the site, not chosen from this table. Values are quoted for reference and must be confirmed against the current edition of each standard at design stage.
Every part of the IT or storage facility protection system has its own test standard
IEC 62305 sets the design. The IEC 62561 series sets the test for each component that carries lightning current. A system holds only if the clamp, the conductor and the electrode each pass their own test.
| Component | What the standard proves | Standard |
|---|---|---|
| Clamps, connectors and bonding parts | Each joint is aged in salt mist and a humid sulphurous atmosphere, then tested with lightning current. Class H is tested at 100 kA and class N at 50 kA. | IEC 62561-1 |
| Conductors and earth electrodes | Sets the material, cross-section and coating of tapes, round conductors and rods. A copper-bonded steel rod carries at least 250 µm of 99.9 % copper. | IEC 62561-2 |
| Isolating spark gaps | Joins metal parts that must stay separate in service, such as insulating flanges and cathodically protected pipes. The gap conducts only during a strike. | IEC 62561-3 |
| Conductor holders and fixings | Holders are tested for mechanical strength after environmental ageing, so the conductor stays in place on roofs, walls and structures. | IEC 62561-4 |
| Earth pit housings and electrode seals | Inspection housings are load tested. Seals are tested where an electrode passes through a waterproofed slab. | IEC 62561-5 |
| Lightning strike counters | The counter records each strike carried by a down conductor. A new count is the trigger for an inspection. | IEC 62561-6 |
| Earth enhancing compounds | The compound is tested for leaching, sulphur content, resistivity and corrosion of the electrode buried in it. | IEC 62561-7 |
| Surge protective devices | Part 11 covers SPDs on AC power, part 21 covers signal and data lines, and part 31 covers the DC side of PV plants. | IEC 61643-11, IEC 61643-21, IEC 61643-31 |
| PE, bonding and earthing conductors | Sets the size, material, joints and continuity of every protective conductor from the earth electrode to the equipment frame. | IEC 60364-5-54, IS 3043:2026, IS 732:2019 |
LPES components are built and comply to the parts listed. Ask for the test report of the specific product with your enquiry. Confirm clause values against the current edition of each standard at design stage.
What goes into your IT or storage facility project
Each card opens the product family in the LPES catalogue.









Areas LPES covers in storage service provider
- IT parks and tech campuses
- BPO and contact centres
- Storage and colocation rooms
- Network operations centres
- UPS, battery and DG systems
- Rooftop masts and microwave links
- Office floors and meeting rooms
- Security, CCTV and access control
Is your IT or storage facility site ready for an inspection?
Six points an Electrical Inspector or an insurer will ask about.
- Every motor and panel above 250 V has two separate earth connections.Reg 43(vii)
- Protective equipotential bonding is installed and was tested before energisation.Reg 43(v), 43(ix)
- Earth-fault loop impedance has been tested for each circuit and each source.Reg 43(xi)
- Earth resistance is tested every year in the dry season and the record is kept.Reg 50(8)
- The lightning protection system has a current risk assessment and inspection record.Reg 38(3)(vi)
- SPDs are fitted at the incomers and their status is checked on rounds.IEC 62305-4
Answer the six points for your site. Nothing is sent anywhere until you ask.
What each person on a IT or storage facility project asks
When did we last prove that every protective conductor is continuous and every breaker will trip on an earth fault?
LPES measures loop impedance and PE continuity circuit by circuit and hands over the record.
Testing & MeasurementLightning to Load
Seven stages, from the first risk assessment to the yearly inspection, with clear ownership at every interface.
Calculated. Coordinated. Implemented. Verified.
- AssessIEC 62305-2 risk assessment, site audit, soil resistivity survey
- DesignLPS, earthing and SPD design with calculations and drawings
- SpecifyBill of materials with LPES part numbers and data sheets
- SupplyProducts from one source, tested to IEC 62561 and IEC 61643
- ImplementInstallation supervision or turnkey execution
- VerifyContinuity, earth resistance and SPD checks, recorded
- AssurePeriodic inspection, monitoring and AMC
LPES Protection Passport. Every project closes with one document set: risk assessment, as-built drawings, product list with part numbers, test records and the inspection plan.
LPES servicesBuilt and comply to
- CEA Safety Regulations 2023
- IEC 62305-1 to -4
- IEC 61643-11 and -21
- IEC 62561 series
- ITU-T K.27
- IEC 60364-5-54
- IS 3043:2026
- NBC 2016
- CEA Safety Regulations 2023
The applicable edition and any project or statutory specification are confirmed at the design stage.
Storage Service Provider lightning protection and earthing: frequently asked questions
Does a server room need its own earth pit?
Related: Earth Bars & Terminals ›
Is fibre enough to protect the network?
Related: Data, Signal & RF Line SPDs ›
Where do SPDs go in an IT building?
Related: Type 1+2 Combined SPDs ›
Can a rooftop telecom mast be installed on our building?
Related: Air Terminal Rods ›
Engineering guides from the LPES knowledge hub
- Earthing of installations with higher protective conductor currentHB-ID-536
- Supplementary bonding and installations with increased shock riskHB-ID-533
- Types of protective earthing conductors and their electrical continuityHB-ID-530
- Earthing conductor and protective bonding conductor sizingHB-ID-528
- Main earthing terminal / main earth busbar (MET)HB-ID-529
- Fault protection by automatic disconnection in TN, TT and IT systemsHB-ID-532
- Measurement of earth fault loop impedance
- Continuity resistance measurement
Related industries
- Data CentresIndustry page
- Network EquipmentIndustry page
- Telecom OEMIndustry page
- Real Estate & InfrastructureIndustry page
More in Digital & Telecom Infrastructure
- Digital & Telecom InfrastructureSector overview
- Network EquipmentIndustry page
- Telecom OEMIndustry page
- Data CentresIndustry page
- All industriesIndustries overview
Your power is connected. Is your protection?
Bring your electrical protection together. Understand your risks. Coordinate your protection. Know who owns each responsibility.
Talk to LPES about a coordinated assessment for your IT or storage facility project, from Lightning to Load. You get: a risk assessment and a protection concept, based on your site layout and single line diagram.